A construction project update presentation for the steering group

A monthly update on a community library build, for project managers reporting to a client, sponsor or steering group. It shows progress and spend against plan, what is in and out of scope, the budget by work package, two options to recover a delay and the milestones to opening day.

Business17 slides · shown in the Kiln template (Premium)

Start free: 2 decks, the first 3 slides of each written. Every slide and PowerPoint download with Premium.

The deck, slide by slide

Every slide as it is designed in Kiln, with its text written out beside it.

  1. 2026
    Millbrook Library Build: Month 4 Update
    Scope, schedule, budget and risks · 14 October 2026 · Owen Clarke, Project Director

    01Cover

    Millbrook Library Build: Month 4 Update

    Scope, schedule, budget and risks · 14 October 2026 · Owen Clarke, Project Director

  2. 02Agenda

    What we'll cover

    • Scope and design
    • Schedule and milestones
    • Budget to date
    • Risks and mitigations
    • Decisions we need
  3. 03Section

    Where the build stands

    Four months in: on budget, but two weeks behind on the steel frame.

  4. 04Key numbers

    The build is on budget and 38% complete

    Foundations and the basement slab are done. The steel frame starts two weeks late after a supplier delay.

    • 38% — Work complete
    • $7.1M — Spent of $18.6M budget
    • 0 — Lost-time incidents
    • 2 wks — Behind on steel frame
  5. 05Chart

    Monthly spend has stayed just under plan since June

    Chart: Planned ($M), Actual ($M) across Jun, Jul, Aug, Sep.

    • Planned ($M): Jun 1.2 · Jul 1.8 · Aug 2.1 · Sep 2.2
    • Actual ($M): Jun 1.1 · Jul 1.7 · Aug 2.1 · Sep 2.2

    Spend doubled as the frame began, yet is $0.2M under plan to date with contingency untouched.

  6. 06At a glance

    The build at a glance

    • Foundations and basement slab complete — All 86 piles and the basement slab were poured by 28 September, passing every structural inspection first time.
    • Steel two weeks late — Supplier backlog.
    • Zero lost-time incidents — 112,000 hours worked.
    • $1.4M contingency intact — Not yet drawn on.
    • Planning conditions met — All 14 discharged.
  7. 07Points

    Three decisions kept the build on budget

    Each was agreed with the council steering group.

    • Switching to a precast concrete basement saved six weeks of formwork and $310K in labour.
    • Ordering the glazing in June locked in prices before a 9% rise across the supply market.
    • Reusing excavated soil for landscaping avoided 1,400 truck trips and $180K in disposal fees.
  8. 08Two columns

    Scope: what is in, and what is out

    In scope

    • Two-storey library, 3,200 m²
    • Children's wing and maker space
    • Rooftop solar and garden

    Out of scope

    • Underground car park
    • Café fit-out, funded by tenant
    • Phase 2 community hall
  9. 09Comparison

    Two options to recover the steel delay

    Resequence works

    • Build the core and stairs first
    • No extra cost
    • Recovers 8 of 10 days

    Add a second crew

    • Weekend steel crew for 6 weeks
    • $96K in extra labour
    • Recovers all 10 days
  10. 10Table

    Budget by work package

    PackageBudgetSpentStatus
    Groundworks$2.9M$2.8MComplete
    Structure$5.4M$3.1MDelayed
    Envelope$4.2M$0.9MOn track
    Fit-out$4.7M$0.3MNot started
  11. 11Timeline

    Four milestones to opening day

    1. Dec 2026Steel frame topped out and the roof deck poured.
    2. Mar 2027Building weathertight, with glazing and cladding complete.
    3. Jul 2027Fit-out finished, shelving installed and systems commissioned.
    4. Sep 2027Handover to the council, and doors open to the public.
  12. 12Process

    How every change request is handled

    1. RaiseSite team logs the change with drawings and a reason.
    2. PriceCost and schedule impact priced within five days.
    3. ApproveSteering group signs off anything over $25K.
    4. BuildChange issued to site with updated drawings.
  13. 13Composed

    One site rhythm runs every work package from design to handover

    1. Design: Drawings frozen per package (Design team)
    2. Procure: Two quotes for every order (Site team)
    3. Build: Daily briefing, weekly look-ahead (Site team)
    4. Inspect: Hold points signed by the engineer (Design team)
    5. Handover: Snag-free sign-off by the council (Site team)

    Meetings

    • Daily: toolbox talk on site
    • Weekly: progress and safety review
    • Monthly: steering group report
    PackageLeadNext milestone
    1StructureMarta KowalskiTopped out, Dec
    2EnvelopeSamuel MwangiWeathertight, Mar
    3Building systemsLeila FarahaniCommissioned, Jul
    4Fit-outOwen ClarkeHandover, Sep

    How we'll run the site

    • Safety first: Every shift starts with a briefing
    • One programme: Same schedule in every meeting
    • Fast decisions: Changes priced within five days

    Success looks like: Doors open in September 2027

  14. 14Image

    What the community will get

    A light-filled, two-storey library on the river, with a children's wing, a maker space and a rooftop garden open to everyone.

    • 3,200 m² across two floors
    • Designed for net-zero operation

    Image: Architectural rendering of a timber and glass community library beside a river

  15. 15Team

    Who is running the site

    • Owen Clarke, Project Director. Accountable to the council.
    • Marta Kowalski, Structures Manager. Steel frame and slabs.
    • Samuel Mwangi, Envelope Manager. Glazing and cladding.
    • Leila Farahani, Building Services Lead. Mechanical and electrical.
  16. 16Quote

    Why the community is behind it

    “My kids have nowhere quiet to do homework. We drive past the site every day just to watch it grow.”

    Parent, Millbrook community consultation
  17. 17Closing

    Recover the steel delay, then hold the line

    Approve the resequenced frame today and the library still opens in September 2027, on budget.

Make your own version

Arcdeck starts from this topic in Kiln. Change it to yours, edit the storyline, and every slide is written for you.

Make a deck like this

Questions

Status in one line, progress and spend against plan, the issues that need a decision, and the next milestones. This example leads with the status, then gives the steel delay two options so the steering group can choose.